Project Information
Kilometer:
72.15KM
Location:
Asphaltic Improvement of some selected roads, NNPC Junction - General Gas Road, Anglican Church Road off Kolapo Ishola Junction Road, Adenihun Crescent Road, Ido Crescent Road, Agodi
Precentage Completed:
41%
Contractor:
Kopek Const. Ltd
Start Date:
Dec 2023
Est. Completion:
May 2025
Progress - 41%
Planning
Construction
Inspection
✓
Construction started
✓
Phase 1 complete